" Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify... "
Cases Decided in the United States Court of Claims ... with Report of ... - Page 215
by United States. Court of Claims, Audrey Bernhardt - 1959
Full view - About this book

Boards of Contract Appeals, Hearings Before a Subcommittee ... 89-2, March 8 ...

United States. Congress. Senate. Select Committee on Small Business - 1966 - 182 pages
...contract price or delivery schedule, or both, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this...receipt by the Contractor of the notification of change, provided, hovyever. that the Contracting Officer, if he decides that the facts justify such action,...
Full view - About this book

Atomic Energy Commission reports v.2, Volume 2

United States Atomic Energy Commission - 1966 - 1040 pages
...price or delivery schedule, or both, and the contract shall be modified in •writing accordingly. Any claim by the Contractor for adjustment under this...receipt by the Contractor of the notification of change : Provided, Tiowever, that the Contracting Officer, if he decides that the facts justify such action,...
Full view - About this book

Independent Offices Appropriations for Fiscal Year 1967, Hearings Before ...

United States. Congress. Senate. Appropriations Committee - 1966 - 1034 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change : Provided, however, that the Contracting Officer, if he decides that the facts justify such action,...
Full view - About this book

Control and Use of Excess Property and Related Foreign Assistance Problems ...

United States. Congress. House. Government Operations - 1967 - 392 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 60 days from the date of receipt by the Contractor of the notification of change, provided, however, that the Contracting Officer, If he decides that the facts justify such action,...
Full view - About this book

Role of Giant Corporations: Hearings, Ninety-first Congress, First Session ...

United States. Congress. Senate. Select Committee on Small Business. Subcommittee on Monopoly - Antitrust law - 1969 - 1736 pages
...ronlract price or delivery schedule, or both, and the contract shall he modified in vviititu- accordingly. Any claim by the Contractor for adjustment under this...of receipt by the Contractor of the notification of chainrc: I'umnW. fcosffner. That the Contracting Officer, if he cWeldjH that the fact* justify such...
Full view - About this book

Establish a Commission on Government Procurement: Hearing ..., Volumes 74-76

United States. Congress. Senate. Committee on Government Operations - Administrative agencies - 1969 - 434 pages
...accordingly. Any claim of the Contractor for adjustment under this clause must be asserted in writing within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however , That the Contracting Officer, if he determines that the facts justify such action,...
Full view - About this book

Hearings, Reports and Prints of the Joint Economic Committee

United States. Congress. Joint Economic Committee - Legislative hearings - 1969 - 1770 pages
...accordingly. Any claim by the Contractor for adjustment under this Clause oust be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts Justify such action,...
Full view - About this book

Hearings, Reports and Prints of the Senate Committee on Government Operations

United States. Congress. Senate. Committee on Government Operations - Executive departments - 1969 - 1762 pages
...accordingly. Any claim of the Contractor for adjustment under this clause must be asserted in writing within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however , That the Contracting Officer, if he determines that the facts justify such action,...
Full view - About this book

Reports of the Tax Court of the United States, Volume 54

United States. Tax Court - Taxation - 1970 - 1856 pages
...accordingly. Any claim of the Contractor for adjustment under thia clause must be asserted in writing within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however. That tie Contracting Officer, if he determines that the facts justify such action,...
Full view - About this book

Industrialized Housing: Hearings, Ninety-first Congress, First ..., Part 1

United States. Congress. Joint Economic Committee. Subcommittee on Urban Affairs - Construction industry - 1969 - 484 pages
...accordingly. Any claim by the Contractor for adjustment under this Clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action,...