| Theodore Minot Clark - Architects - 1894 - 424 pages
...Owner to the Contractor, but if Form i. such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner. The expense...the Owner as herein provided, either for furnishing mate rials or for finishing the work, and any damage incurred through such default, shall be audited... | |
| Earle Abbott Merrilol - Electric lighting - 1896 - 232 pages
...by the Owner to the Contractor, but if such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner, The expense...and any damage incurred through such. default, shall be audited and certified by the Architects, whose certificate thereof shall be conclusive upon the... | |
| Earle Abbott Merrill - Electric lighting - 1896 - 222 pages
...by the Owner to the Contractor, but if such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner. The expense...and any damage incurred through such. default, shall be audited and certified by the Architects, whose certificate thereof shall be conclusive upon the... | |
| Earle Abbott Merrill - Electric lighting - 1896 - 232 pages
...by the Owner to the Contractor, but if such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner. The expense...finishing the work, and any damage incurred through suchr default, shall be audited and certified by the Architects, whose certificate thereof shall be... | |
| Law reports, digests, etc - 1896 - 1262 pages
...the owner to the contractors; but, if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense...furnishing materials or for finishing the work, and any damages Incurred through such default, shall be audited and certified by the architects, whose certificate... | |
| New York (State). Supreme Court. Appellate Division - Law reports, digests, etc - 1902 - 762 pages
...owner in finishing the work, snch excess shall be paid by the owner to the contractor ; " and that " the expense incurred by the owner as herein provided,...and any damage incurred through such default, shall be audited and certified by the architect or engineer, as the case may be, whose certificate shall... | |
| Law reports, digests, etc - 1896 - 1218 pages
...totbe contractors, but if such expense shall exceed such unpaid balance the contractors shall pay t lie difference to the owner. The expense incurred by the owner, as herein provided, either by furnishing material, or for finishing the work, and any damage incurred through such default, shall... | |
| Illinois. Appellate Court, Edwin Burritt Smith, Martin L. Newell - Law reports, digests, etc - 1897 - 710 pages
...the difference to the party of the second part. The expense incurred by the party of the second part, as herein provided, either for furnishing materials...and any damage incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties.... | |
| Law reports, digests, etc - 1897 - 1148 pages
...should not complete the building, the owner may do so, and charge the expense to the contractor; and "the expense incurred by the owner as herein provided,...for furnishing materials or for finishing the work, shall be audited and certified by the architect, and his certificate thereof shall be conclusive upon... | |
| Washington (State). Supreme Court, Eugene Genroy Kreider - Law reports, digests, etc - 1897 - 812 pages
...should not complete the building, the owner may do so and charge the expense to the contractor, and " the expense incurred by the owner as herein provided,...either for furnishing materials or for finishing the Oct. 1896.] Opinion of the Court— ANDERS, J. work, shall be audited and certified by the architect,... | |
| |