Page images
PDF
EPUB

ever during the month of September. The suit was brought 19th September, 1912, to recover for coke delivered during July. The contention on part of defendants was that the contract set up in the affidavit of defense was entire, and that there could be no recovery by plaintiff for any partial performance. A rule for a judgment for want of a sufficient affidavit of defense was made absolute, and judgment followed. * * *

*

Where a question of this kind arises, it is the intention of the parties that controls, and not the divisibility of the subject, * * and this intention is to be collected from the words employed, where the intention can be clearly derived therefrom. When, as understood in their ordinary sense, the words do not disclose the manner and intent to which the parties intended to be bound, resort must be had to rules of construction as aids. Having regard simply to the words employed in this contract, the inference that the contract was intended to be entire would be quite as reasonable as that it was intended to be divisible. If there are provisions which indicate that a divisible contract was intended, there are others which quite as clearly indicate the opposite.

The distinguishing mark of a divisible contract is that it admits of apportionment of the consideration on either side so as to correspond to the unascertained consideration on the other side. Where such a purpose appears in the contract, or is clearly deducible therefrom, it is allowed great significance when ascertaining the intention of the parties. It is a mistake, however, to suppose that in every case it is conclusive in itself. It is determining only when there are no opposing signs or marks. Where these latter are present it becomes a question of preponderance. * *

*

While it is not averred in the affidavit that failure to complete the contract of plaintiffs would have affected the sale in this case, it is a reasonable inference, in view of the situation of the parties and the object contemplated, that it would have done so. It was not required that it should have been averred in the affidavit. The courts always seek to avoid, as far as they consistently can, a construction that would render a contract ineffectual. The present is a case in which the manifest purpose of the agreement would be defeated were it held to be a divisible contract, thereby allowing the plaintiff not simply to disappoint the defendants in what it was intended they should receive for a specific and express purpose, but requiring from the defendants payment for so much performance as met the pleasure, convenience, and advantage of the plaintiff. As against such construction, the defendants might well reply, in hæc foedera non venimus. We have discussed the case as though the contract were as averred in the affidavit. The defendants should be allowed an opportunity to prove the averment. The judgment is reversed.

*

STEWART v. NEWBURY et al.

(Court of Appeals of New York, 1917. 220 N. Y. 379, 115 N. E. 984,

2 A. L. R. 519.)

Action by Alexander Stewart against Herbert A. Newbury and others, doing business under the firm name and style of the Newbury Manufacturing Company. From a judgment for plaintiff, defendants appeal.

CRANE, J. The defendants are partners in the pipe fitting business under the name of Newbury Manufacturing Company. The plaintiff is a contractor and builder residing at Tuxedo, N. Y. Plaintiff agreed to do all excavation and concrete work upon a foundry building for defendants. The parties agreed as to amounts to be paid for the work. Nothing was said in writing about the time or manner of payment.

* * *

In July the plaintiff commenced work and continued until September 29th, at which time he had progressed with the construction as far as the first floor. He then sent a bill for the work done up to that date. for $896.35. The defendants refused to pay the bill and work was discontinued. * * *

In this action, which is brought to recover the amount of the bill presented, as the agreed price and $95.68 damages for breach of contract, the plaintiff had a verdict for the amount stated in the bill, but not for the other damages claimed, and the judgment entered thereon has been affirmed by the Appellate Division. The appeal to us is upon. exceptions to the judge's charge.

* * *

The jury was plainly told that if there were no agreement as to payments, yet the plaintiff would be entitled to part payment at reasonable times as the work progressed, and if such payments were refused he could abandon the work and recover the amount due for the work performed.

This is not the law. Counsel for the plaintiff omits to call our attention to any authority sustaining such a proposition and our search reveals none. In fact, the law is very well settled to the contrary. This was an entire contract. * * * Where a contract is made to perform work and no agreement is made as to payment, the work must be substantially performed before payment can be demanded.

* * *

The judgment should be reversed, and a new trial ordered.

NORRINGTON v. WRIGHT et al.

(Supreme Court of the United States, 1885. 115 U. S. 188, 6 Sup. Ct. 12, 29 L. Ed. 366.)

GRAY, J. This was an action of assumpsit, brought by Arthur Norrington, a citizen of Great Britain, against James A. Wright and others, citizens of Pennsylvania, trading under the name of Peter Wright & Sons, upon the following contract:

"Philadelphia, January 19, 1880. "Sold to Messrs. Peter Wright & Sons, for account of A. Norrington & Co., London: Five thousand (5,000) tons old T iron rails, for shipment from a European port or ports, at the rate of about one thousand (1,000) tons per month, beginning February, 1880, but whole contract to be shipped before August 1, 1880, at forty-five dollars ($45.00) per ton of 2240 lbs. customhouse weight, ex ship Philadelphià. Settlement, cash, on presentation of bills accompanied by customhouse certificate of weight. 'Edward J. Etting, Metal Broker." The plaintiff shipped from various European ports 400 tons by one vessel in the last part of February, 885 tons by two vessels in March, 1,571 tons by five vessels in April, 850 tons by three vessels in May, 1,000 tons by two vessels in June, and 300 tons by one vessel in July, and notified to the defendants each shipment. The defendants received and paid for the February shipment upon its arrival in March, and

in April gave directions at what wharves the March shipments should be discharged on their arrival; but on May 14th, about the time of the arrival of the March shipments, and having been then for the first time informed of the amounts shipped in February, March, and April, they gave Etting written notice that they should decline to accept the shipments made in March and April, because none of them were in accordance with the contract; and in answer to a letter from him of May 16th, wrote him on May 17th, as follows: "We are advised that what has occurred does not amount to an acceptance of the iron under the circumstances, and the terms of the contract. You had a right to deliver in parcels, and we had a right to expect the stipulated quantity would be delivered until the time was up in which that was possible. * * * If we are mistaken as to our obligation for the February and March shipments, of course we must abide the consequences; but if we are right, you have not performed your contract, as you certainly have not for the April shipments. There is then the very serious and much debated question, as we are advised, whether the failure to make the stipulated shipments in February or March has absolved us from the contract. If it does, we of course will avail ourselves of this advantage."

[ocr errors]

On May 18th Etting wrote to the defendants, insisting on their liability for both past and future shipments: *You say in your last paragraph that you shall avail yourselves of the advantage, if you are absolved from the contract; but, as you seem to be in doubt whether you can set up that claim or not, I should like to know definitely what is your intention."

On May 19th the defendants replied: "We do not read the contract as you do. We read it as stipulating for monthly shipments of about one thousand tons, beginning in February, and that the six months' clause is to secure the completion of whatever had fallen short in the five months. As to the meaning of 'about,' it is settled as well as such a thing can be; and certainly neither the February, March, nor April shipments are within the limits. * * * You ask us to determine whether we will or will not object to receive further shipments because of past defaults. We tell you we will if we are entitled to do so, and will not if we are not entitled to do so. We do not think you have the right to compel us to decide a disputed question of law to relieve you from the risk of deciding it yourself. You know quite as well as we do what is the rule and its uncertainty of application." * * * From the date of the contract to the time of its rescission by the defendants, the market price of such iron was lower than that stipulated in the contract, and was constantly falling. After the arrival of the cargoes, and their tender and refusal, they were sold by Etting, with the consent of the defendants, for the benefit of whom it might concern.

At the trial the plaintiff contended: (1) That under the contract he had six months in which to ship the 5,000 tons, and any deficiency in the earlier months could be made up subsequently, provided that the defendants could not be required to take more than 1,000 tons in any one month; (2) that, if this was not so the contract was a divisible contract, and the remedy of the defendants for a default in any month was not by rescission of the whole contract, but only by deduction of the damages caused by the delays in the shipments on the part of the plaintiff. But the court instructed the jury that if the defendants, at

the time accepting the delivery of the cargo paid for, had no notice. of the failure of the plaintiff to ship about 1,000 tons in the month of February, and immediately upon learning that fact gave notice of their intention to rescind, the verdict should be for them. The plaintiff excepted to this instruction, and, after verdict and judgment for the defendants, sued out this writ of error.

In the contracts of merchants, time is of the essence. The time of shipment is the usual and convenient means of fixing the probable time. of arrival, with a view of providing funds to pay for the goods, or of fulfilling contracts with third persons.

* * *

The contract sued on is a single contract for the sale and purchase of 5,000 tons of iron rails, shipped from a European port or ports for Philadelphia. The subsidiary provisions as to shipping in different. months, and as to paying for each shipment upon its delivery, do not split up the contract into as many contracts as there shall be shipments, or deliveries of so many distinct quantities of iron. The times of shipment, as designated in the contract, are "at the rate of about 1,000 tons per month, beginning February, 1880, but whole contract to be shipped before August 1, 1880." These words are not satisfied by shipping one-sixth part of the 5,000 tons, or about 833 tons, in each of the six months which begin with February and end with. July. But they require about 1,000 tons to be shipped in each of the five months from February to June inclusive, and allow no more than slight and unimportant deficiencies in the shipments during those months to be made up in the month of July. The contract is not one for the sale of a specific lot of goods, identified by independent circumstances such as all those deposited in a certain warehouse, or to be shipped in a particular vessel, or that may be manufactured by the seller, or may be required for use by the buyer, in a certain mill-in which case the mention of the quantity, accompanied by the qualification of "about," or "more or less," is regarded as a mere estimate of the probable amount, as to which good faith is all that is required of the party making it. But the contract before us comes within the general rule: "When no such independent circumstances are referred to, and the engagement is to furnish goods of a certain quality or character to a certain amount, the quantity specified is material, and governs the contract. The addition of the qualifying words 'about,' 'more or less,' and the like, in such cases, is only for the purpose of providing against accidental variations arising from slight and unimportant excesses or deficiencies in number, measure, or weight." The seller is bound to deliver the quantity stipulated, and has no right either to compel the buyer to accept a less quantity, or to require him to select part out of a greater quantity; and when the goods are to be shipped in certain proportions monthly, the seller's failure to ship the required quantity in the first month gives the buyer the same right to rescind the whole contract that he would have had if it had been agreed that all the goods should be delivered at once.

The plaintiff, instead of shipping about 1,000 tons in February and about 1,000 tons in March, as stipulated in the contract, shipped only 400 tons in February, and 885 tons in March. His failure to fulfill the contract on his part in respect to these first two installments justified the defendants in rescinding the whole contract, provided they distinctly and seasonably asserted the right of rescission. The defendants, immediately after the arrival of the March shipments, and as

soon as they knew that the quantities which had been shipped in February and in March were less than the contract called for, clearly and positively asserted the right to rescind, if the law entitled them to do so. Their previous acceptance of the single cargo of 400 tons shipped in February was no waiver of this right, because it took place without notice or means of knowledge that the stipulated quantity had not been shipped in February. The price paid by them for that cargo being above the market value, the plaintiff suffered no injury by the omission of the defendants to return the iron; and no reliance was placed on that omission in the correspondence between the parties.

* * *

For these reasons we are of opinion that the judgment below should be affirmed.

HELGAR CORP. v. WARNER'S FEATURES, Inc.

(Court of Appeals of New York, 1918. 222 N. Y. 449, 119 N. E. 113.) Action by the Helgar Corporation against Warner's Features, Incorporated.

CARDOZO, J. The plaintiff's assignor made a contract with the defendant for the sale of films for moving pictures. At least one film was to be delivered every month. Deliveries were to begin in November, 1913, and to end in October, 1914. The price was fixed at eight cents per foot, and payment for each film was to be made within 30 days after exhibition to the public. By way of additional compensation, the defendant was also to pay one-half of the net profits realized by it as the result of foreign sales.

The plaintiff, having received an assignment of the contract, delivered pictures of the value at the contract rate of nearly $10,000. The price was payable on December 24, 1913. The finding is that payment was then demanded, and that "the defendant refused and neglected to pay the same or any part thereof, nor did the defendant offer or tender a part payment of said amount or offer to pay the same in installments." Two days later this action was begun. The plaintiff alleged its election to terminate the contract by reason of the breach. Judgment was demanded for the price of the films delivered, and also for the profits that would have been gained through the completion of the contract. The referee gave judgment for the price, but refused to award the profits. In his opinion, he put his refusal upon the ground that the, failure to make punctual payment was not accompanied by acts or words evincing repudiation or abandonment. The Appellate Division added $2.000 to the judgment. This was the estimated value of foreign rights which attached to the sales already made. That value was thought to be recoverable as an incident to the price. With this modification, the judgment was unanimously affirmed. There are cross-appeals in this court.

The rights of vendor and vendee upon the breach of an installment contract are now regulated by statute. The rule is to be found in section 45, subdivision 2, of the statute governing sales of goods: "Where there is a contract to sell goods to be delivered by stated installments, which are to be separately paid for, and the seller makes defective deliveries in respect of one or more installments, or the buyer neglects or refuses to take delivery of or pay for one or more installments, it depends in each case on the terms of the contract and the circumstances of the case whether the breach of contract is so ma

« PreviousContinue »