STATEMENT OF APPROPRIATIONS FOR PUBLIC BUILDINGS IN COURSE OF CONSTRUCTION UNDER CHARGE OF TREASURY DEPARTMENT. UNITED STATES CUSTOM-HOUSE, ALBANY, N. Y. Building authorized by act of March 12, 1872, (vol. 17, p. 39,) which limited its cost to $350,000, but made no appropriation, and required the site to be given by city of Albany. Act of June 10, 1872, (vol. 17, p. 353,) appropriated for commencement of the work. Act of March 3, 1873, (vol. 17, p. 523,) appropriated for part purchase of site, the balance to be paid by city of Albany Act of June 23, 1874, (vol 18, p. 228,) appropriated for balance due on purchase... $100,000 00 150,000 00 5,000 00 Total amount appropriated Amount expended for site to September 30, 1875..... Balance of appropriation available in Treasury September 30, 1875.. Act of March 3, 1875, (vol. 18, p. 394,) appropriates for continuation of building.. UNITED STATES COURT-HOUSE AND POST-OFFICE, ATLANTA, GA. Cost of building limited by act of February 12, 1873, (vol. 17, p. 436,) to $110,000, and appropriated Act of June 23, 1874, (vol. 18, p. 228,) extends limit of building to $250,000. $110,000 00 50,000 00 Balance of appropriation available in the Treasury September 30, 1875 UNITED STATES POST-OFFICE AND SUBTREASURY, BOSTON, MASS. Act of March 3, 1873, (vol. 17, p. 524,) authorized the purchase of additional land and extension of the building, and appropriated..... $630,000 00 Total amount appropriated. Act of March 3, 1875, (vol. 18, p. 408,) authorized the expenditure of $59,344.02 for furniture to be paid from the balance of appropriation.. $630,000 00 59,344 02 Balance available for purchase of site and extension of building 570,655 98 $386,886 42 53, 626 88 Balance of appropriation available in Treasury September 30, 1875 UNITED STATES CUSTOM-HOUSE, SUBTREASURY, ETC., CHICAGO, ILL Act of December 21, 1871, (vol. 17, p. 24,) limits the cost $2,000,000 00 750,000 00 Act of March 3, 1875, (vol. 18, p. 394,) appropriates for continuation 750,000 00 Total amount appropriated... $4, 300, 000 00 Amount expended for site to September 30, 1875 ........ Amount expended for the construction of the building to date, September 30, 1875.... Balance of appropriation remaining in Treasury September 30, 1875 $1,259,385 65 2,062,907 43 977,706 92 4,300,000 00 $4,300,000 00 UNITED STATES CUSTOM-HOUSE AND POST-OFFICE, CINCINNATI, OHIO. Act of March 12, 1872, authorized purchase of site, limited the cost thereof to $300,000 but made no appropriation. Act of June 10, 1872, (vol. 17, p. 352,) limited cost of site Act of March 3, 1875, (vol. 18, p. 394,) appropriates. Total amount appropriated Total amount expended for site to date, September 30, Total amount expended for construction of building to Balance of appropriation remaining in Treasury Septem- 1875. $700,000 00 750,000 00 600, 000 00 $708,036 60 1,064, 024 02 877,939 38 $2,650, 000 00 2,650,000 00 2,650,000 00 UNITED STATES CUSTOM-HOUSE, COURT-HOUSE, POST-OFFICE, ETC., AT EVANSVILLE, IND. Act of January 16, 1873, (vol. 17, p. 411,) limits cost of building and site to $200,000. Act of March 3, 1873, (vol. 17, p. 541,) appropriates.... Act of June 23, 1874, (vol. 18, p. 227,) limits cost of building, exclusive of site, to $200, 000, and appropriates... Act of March 3, 1875, (vol. 18, p. 394,) appropriates for continuation. Total amount appropriated.... Amount expended for site to date of September 30, 1875.. Balance of appropriation available in Treasury September 30, 1875... UNITED STATES CUSTOM-HOUSE AND POST-OFFICE, FALI. RIVER, MASS. Act of May 21, 1872, (vol. 17, p. 140,) limited cost of building and site to $200,000. Act of March 3, 1873, (vol. 17, p. 523,) appropriated for site and building... Act of March 3, 1875, (vol. 18, p. 394,) repeals limit, and appropriates Total amount appropriated.... Amount expended for site to date of September 30, 1875. Amount expended for construction of building to September 30, 1875.... Balance of appropriation available in Treasury September 30, 1875.. $200,000 00 UNITED STATES COURT-HOUSE AND POST-OFFICE, GRAND RAPIDS, MICH. Act of February 21, 1873, (vol. 17, p. 470,) authorized the purchase of site and the construction of a building, limiting cost to $200,000. Act of June 23, 1874, (vol. 18, p. 228,) appropriates for site and legal expenses.. $70,000 00 Act of March 3, 1875, (vol. 18, p. 395,) appropriates for continuation 50,000 00 Total amount appropriated.... Amount expended for site to date of September 30, 1875.. Amount expended for construction of building to September 30, 1875..... Balance available in Treasury, September 30, 1875. UNITED STATES CUSTOM-HOUSE AND POST-OFFICE, HARTFORD, CONN. Act of March 18, 1872, (vol. 17, p. 42,) authorizes the erection of building, and limits the cost to $300,000. ing to $400,000, and appropriates Act of March 3, 1875, (vol. 18, p. 395,) appropriates Total amount appropriated (Site donated.) Act of June 10, 1872, (vol. 17, p. 353,) appropriates..... $100,000 00 150,000 00 100,000 00 $350,000 00 Amount expended on construction of building to September 30, 1875.. $318, 164 70 Balance of appropriation available in Treasury September 30, 1875. Balance of appropriation remaining in Treasury September 30, 1875. Amount expended for site to September 30, 1875 UNITED STATES ASSAY-OFFICE, HELENA, MONT. Act of May 12, 1874, (vol. 18, p. 45,) appropriates for the construction of the building, (including necessary fixtures and apparatus,) and limits the cost of same to... Total amount appropriated $50,000 00 UNITED STATES COURT-HOUSE AND POST-OFFICE, LINCOLN, NEBR. Act of February 21, 1873, (vol. 17, p. 470,) authorizes the erection of building, and appropriates, (limited cost).. $130,000 00 Total amount appropriated Amount expended for site, (advertising, &c.,) September 30, 1875... $130,000.00 Balance of appropriation available in the Treasury September 30, 1875 Amount expended on construction of building to date, UNITED STATES CUSTOM-HOUSE, LOUISVILLE, KY. Act of February 19, 1875, (vol. 18, p. 332,) authorizes the purchase of additional site, and appropriates $12,500 00 Total amount appropriated $12,500 00 |