" ... of the Contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid ; but no such allowance shall be made unless a claim therefor is... "
Electric Lighting Specifications for the Use of Engineers and Architects - Page 211
by Earle Abbott Merrill - 1896 - 213 pages
Full view - About this book

Reports of Cases at Law and in Chancery Argued and Determined in ..., Volume 255

Illinois. Supreme Court - Law reports, digests, etc - 1913 - 712 pages
...or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no such allowance shall be made unless a claim therefor is presented, in writing, to the architect within forty-eight hours of the occurrence of such delay." The plaintiff then offered in...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 66

United States. Court of Claims - Law reports, digests, etc - 1929 - 868 pages
...allowed. " which extended period shall be determined and fixed by the Director [of the Veterans' Bureau] ; but no such allowance shall be made unless a claim therefor is presented in writing to the Director within forty-eight hours of the occurrence of such delay." and that $25.00 per day was to...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 131

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1955 - 908 pages
...equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless a claim therefor is presented in writing to the Contractor within seven (7) days of the occurrence of such delay. The subcontractor shall not have,...
Full view - About this book

The Pacific Reporter, Volume 68

Law reports, digests, etc - 1902 - 1166 pages
...to be done shall be extended for a period equivalent to the delay so caused, but no such extension shall be made unless a claim therefor Is presented In writing to the owner within 24 hours after the delay, — the duration of the extension to be certified by the owner;...
Full view - About this book

The Southwestern Reporter, Volume 147

Law reports, digests, etc - 1912 - 1356 pages
...extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall be made, unless a claim therefor Is presented In writing to the architect within 48 hours after the occurrence of such delay. Thus it will be seen that the contract...
Full view - About this book

Arkansas Reports: Cases Determined in the Supreme Court of the ..., Volume 104

Arkansas. Supreme Court - Law reports, digests, etc - 1913 - 694 pages
...extended for a period equal to the time lost by reason of any such cause. But it also provides that no such allowance shall be made unless a claim therefor is presented in writing to the architect within forty-eight hours after the occurrence of such delay. Thus it will be seen that the...
Full view - About this book

Official Report ... Annual Convention, Volume 8, Part 1894

National Association of Builders of the United States of America - Building - 1894 - 274 pages
...be for the protection of the contractor. For the protection of the architect, we put this in : — But no such allowance shall be made unless a claim...twenty-four hours of the occurrence of such delay. four hours to make good your claim. Now the duration or existence of such things, if they are not satisfactory...
Full view - About this book

Transactions of the American Society of Mechanical Engineers, Volume 22

American Society of Mechanical Engineers - Mechanical engineering - 1901 - 1776 pages
...happen by fire, lightning, earthquake or cyclone, or by the abandonment of the work by the employees through no default of the Contractor, then the time...hours of the occurrence of such delay. The duration of inch extension shall be certified to by the Architects, but appeal from their decision may be made...
Full view - About this book

Reports of Cases Argued and Determined in the Supreme Court of ..., Volume 112

Wisconsin. Supreme Court, Abram Daniel Smith, Philip Loring Spooner, Obadiah Milton Conover, Frederic King Conover, Frederick William Arthur, Frederick C. Seibold - Law reports, digests, etc - 1902 - 780 pages
...for the completion of the building should be extended for a period equivalent to the time so lost; " but no such allowance shall be made unless a claim therefor is presented in writing to the architect within twenty-four hours of the occurrence of such delay. The duration of such extension...
Full view - About this book

Reports of Cases Determined in the Supreme Court of the State of ..., Volume 28

Washington (State). Supreme Court, Eugene Glenroy Kreider - Law reports, digests, etc - 1903 - 840 pages
...to be done shall be extended for a period equivalent to the delay so caused, but no such extension shall be made unless a claim therefor is presented in writing to the owner within twenty-four hours after the delay, — the duration of the extension to be certified by...
Full view - About this book